Lessons Learned from Implementation of a Successful PPP Program: #5 Complying With Environmental And Social Performance Standards

GET FiT Uganda is a Public-Private Partnership (PPP) program managed by KfW in cooperation with the Ugandan Government. The program leverages commercial investment in small-, and medium sized Renewable Energy (RE) projects in Uganda.

Developers were often unable to contextualize and apply standards and regulations to their project-specific setting. Most developers gradually overcame limitations, but not without considerable additional efforts from both developers and the GET FiT Programme. Similar PPP programmes could benefit from modifications to programme design and implementation based on GET FiT Uganda experiences.

Info

References

Knowledge Lab
Uganda

Related Documents

Document Group

Lessons Learned from Implementation of a Successful PPP Program